TOTAL VALUE
£60M
COMPLETED
2003

Project Description

The project became a highly successful partnership between Muse, several of its sister companies and Rolls-Royce which delivered a totally integrated solution for a new production facility near Glasgow Airport.

The first phased handover of 4,320 sqm of production space took place in March 2003 with the handover of the fitted-out facility following nine months later. Muse also transferred over 1,000 new and existing machine tools and items of equipment from the existing Hillington and Bristol facilities, with this operation carefully co-ordinated in order to minimise downtime of the vital production cells.

As well as housing production plant, the building incorporates modern office accommodation, testing and product development facilities and extensive welfare areas for the 1,000 staff employed there.